Variations and change orders: get them signed before work starts

Almost every final-account argument starts with a sentence like "while you're here, could you also...". Here is how to turn that sentence into a signed variation in minutes, before anyone picks up a tool.

5 min read Corporate Interactive UK

Sales quoting: a pen on a coral gradient

Lachlan runs a small fit-out company in Manchester. On a café refurbishment last year the client asked, over a coffee on site, for the counter to move 600mm and for two extra sockets behind it. Lachlan said yes, it would be "a few hundred quid". The job finished on time. The final invoice showed £1,140 for the change, because moving the counter meant re-routing a waste pipe nobody had mentioned. The client paid the original contract sum and disputed the rest for four months.

Nobody lied. Both remembered the conversation differently, and nothing was written down. That is the whole problem with verbal variations, and it is entirely avoidable.

Why spoken changes go wrong

A variation changes the deal you both signed. If the change is only spoken, three things are left open: exactly what the extra work is, what it costs, and whether it moves the finish date. Each side fills the gaps with the most favourable version.

The law does not rescue you from a missing price either. For consumer jobs, the Consumer Rights Act 2015 treats things the trader says to the customer as part of the contract where the customer relies on them (section 50). A casual "a few hundred quid" can become the figure you are held to. And where no price was fixed at all, section 51 says the consumer must pay a reasonable price, and no more. What is reasonable then becomes a question of fact, which is a polite way of saying an argument.

In business-to-business construction work, either party can refer a dispute to adjudication at any time under section 108 of the Housing Grants, Construction and Regeneration Act 1996, and the adjudicator must normally decide within 28 days of referral. That route is quick, but it costs money and goodwill, and the adjudicator will want paperwork. A signed variation is the cheapest evidence you will ever produce. (Those adjudication rules do not apply to contracts with a residential occupier for work on their own home.)

What a variation document should contain

Keep it to one page. It needs:

  1. A reference number and the original contract or quote it changes, such as "Variation 3 to Quote Q-2417".
  2. Who asked for it and when. "Requested by Cheryl, site manager, 14 May."
  3. What changes, in plain words, with a photo or marked-up drawing if it helps.
  4. What is added and what is removed. Omissions matter. If the client drops the feature wall, show the credit.
  5. The price of this variation, broken into labour, materials and any plant or skips, plus VAT at the right rate.
  6. The effect on time. "Adds two working days. Revised completion 23 May." Or "No effect on completion."
  7. The running total: original contract value, variations approved so far, this variation, new contract value.
  8. Payment terms for the extra, if they differ from the main contract.
  9. A signature and date from someone with authority to approve spending.

Item 7 is the one most firms skip, and it is the one that prevents the end-of-job shock. A client who signs a variation showing the contract rising from £18,400 to £21,250 cannot say later that nobody told them.

Getting sign-off on the spot

The moment a change is asked for is the moment to price it, while everyone is standing in the same room. Waiting until the evening invites the "we'll sort it out at the end" habit.

Have a short routine your team can follow:

  • Note the request and take photos.
  • Price it there and then if it is simple, using your standard rates. If it needs a supplier price, say so and send it the same day.
  • Send the variation to the client's phone and ask them to approve it before work starts.
  • If they will not sign, do not do the work. Carry on with the agreed scope and log the request.

Where an urgent change cannot wait, for example a safety issue found behind a wall, make it safe, photograph everything and get a variation signed for the remedy within 24 hours. Record that the client was told.

If the client is a homeowner and you agree extra work in their home, the cancellation rules for off-premises contracts may need a look. Our guide to quoting homeowners and their cancellation rights covers how that works.

Track the whole contract, not just the change

On any job with more than a couple of variations, keep a simple register:

No.DescriptionStatusValueTime
V1Extra sockets behind counterApproved 2 May£3200 days
V2Re-route waste pipeApproved 9 May£8201 day
V3Omit feature wallApproved 14 May−£4500 days
V4Upgrade to oak worktopAwaiting client£1,2602 days

The register answers the three questions every client asks near the end: how much, how long, and what did I agree to. It also helps you spot scope creep early. If variations pass 10% of the original value, it is worth a conversation about budget before the next one.

Keep pending variations visible. A change the client has not yet approved is not revenue, and your team should not be building it.

Variations in QuoteCloud

QuoteCloud treats a variation as just another short document that links back to the job.

  • Start from a variation template set up for change orders and signed variations, with the original quote reference, a description block, photos and the running total already laid out.
  • Price the change in an interactive pricing table with quantities, credits for omitted items and VAT at the right rate on each line. Where there is a choice, such as standard or oak worktop, add the upgrade as an option the client can tick.
  • Send it from site on a phone with quotes on mobile, and the client signs on their own screen with the built-in electronic signature inside the quote. Each signature records a verification code, the time, IP address and device.
  • You are notified when the client first opens it, and the document's status moves from Sent to Opened to Accepted, so the office knows which variations are approved without ringing the site.
  • If the variation needs money up front, such as a deposit for special-order materials, the client can pay by card through Stripe or by PayPal when they accept.

Darren, who runs a heating firm in Derby, has a rule his engineers like: no signature on the phone, no spanner on the pipe. It has cut his final-account disputes to almost nothing, and his clients say they like seeing the total before they say yes.

This is general information, not legal advice. If you would like to see a variation template set up for your trade, get in touch.