Writing a scope of works that prevents disputes: a UK checklist

Most disputes are not about bad work. They are about two people reading the same quote and picturing different jobs, and a well-built scope of works is how you close that gap before anyone signs.

5 min read Corporate Interactive UK

Sales quoting: a pen on a coral gradient

"Supply and fit new kitchen." Five words, and a decorator in Reading has heard every possible reading of them. To the customer, it meant the kitchen, the worktops, the tiling, the plastering after the old units came out, the new lighting and taking the old units away. To the decorator's fitter, it meant the units and the worktops. The gap between those two pictures was worth £2,300, and it surfaced on day four.

A scope of works exists to make that gap visible before the contract is signed, when it costs nothing to fix. Here is how to write one that both sides read the same way.

Start with the outcome, then the tasks

Open with one or two sentences that describe the finished result in the customer's terms. "A fully fitted kitchen ready to cook in, with walls plastered and painted, new under-cabinet lighting and the old kitchen removed from site."

Then list the work in the order it will happen. Ordering does two jobs. It shows the customer you have thought the job through, and it exposes steps you forgot to price. If you cannot write "make good the plaster after removing the old units" in the sequence, you probably have not costed it.

Be precise about quantities and specification wherever you can: "14 linear metres of 40mm laminate worktop", not "worktops". Where the customer is choosing a finish later, say so and say what the price allows for.

Inclusions and exclusions

Every scope needs both lists, and the exclusions list is the one that prevents arguments.

Inclusions say what is in the price. Write them as things the customer will see or receive.

Exclusions say what is not in the price, especially anything a reasonable customer might assume is included. Good candidates are:

  • making good and redecoration after your work
  • removal of waste, or of the customer's old items
  • building control or planning fees
  • work to services you did not install, such as existing wiring or pipework
  • out-of-hours working
  • items supplied by the customer, and fitting them

An exclusion is not an admission that you will not do the work. It is a promise to price it separately if it is wanted. Many firms add a short line: "Excluded items can be quoted on request."

Assumptions

Assumptions are what you believed to be true when you priced the job. Writing them down converts hidden risks into agreed facts. Typical assumptions:

  1. Clear access to the work area during working hours, 8am to 5pm on weekdays.
  2. Parking available within 50 metres of the entrance.
  3. Existing floor is level and sound.
  4. No asbestos-containing materials in the work area.
  5. Electricity and water available on site at no charge.

If an assumption turns out to be wrong, the extra work becomes a variation, priced and signed before it goes ahead. Our guide to getting variations signed before work starts covers that step.

Client responsibilities

Customers have jobs too. List them so nobody is surprised:

  • choosing and confirming finishes by a stated date
  • clearing furniture and personal items
  • arranging access, keys or alarm codes
  • obtaining landlord, freeholder or management company consent where needed
  • supplying any items they have chosen to buy themselves, on time and undamaged

Attach a consequence where it matters. "If tiles are not chosen by 4 March, the start date will move to the next available slot."

Provisional sums and prime cost items

Some things cannot be priced exactly at quote stage. Two tools handle them honestly:

  • A provisional sum is an allowance for work that cannot yet be defined, such as repairs to timbers you will only see when the floor is up. State what it covers and that the final cost will be charged at your stated rates.
  • A prime cost (PC) sum is an allowance for an item the customer will choose, such as a tap or a light fitting. State the allowance and how you will adjust for a cheaper or dearer choice, including any handling margin.

Show both clearly, separately from the fixed price, and explain them in a sentence each. A customer who sees "Provisional sum, timber repairs: £600" will not be shocked by a final bill of £480 or £720. One who never saw it will be.

ElementFixed or variableExample wording
Fixed priceFixedSupply and fit units and worktops as listed: £8,950
Provisional sumVariableRepairs to floor joists if required: allowance £600 at £45 per hour plus materials
PC sumVariableKitchen tap: allowance £180; difference charged or credited
ExclusionNot includedRedecoration of adjoining rooms

Why plain wording matters in law as well

With consumer customers, unclear wording tends to work against the business that wrote it. Under the Consumer Rights Act 2015, written terms must be transparent: in plain and intelligible language and legible (section 68). If a term could have different meanings, the meaning most favourable to the consumer prevails (section 69). And things you say or write to the customer about the service can become part of the contract where the customer relies on them (section 50). A clear, specific scope is your best protection against all three.

This is general information, not legal advice.

Building scopes in QuoteCloud

A scope works best when it is part of the quote, not a separate attachment the customer never opens.

  • Set up a scope of works template based on statements of work, with sections for the outcome, task list, inclusions, exclusions, assumptions and client responsibilities.
  • Use the 20 content blocks to add photos of the existing site, an FAQ on what is excluded, and a Gantt chart for the sequence.
  • Put fixed items, provisional sums and PC sums in separate pricing tables, each with VAT on the right lines, so the variable parts are never hidden in the total.
  • Customers can comment on the exact line they are unsure about before they sign, which turns a day-four argument into a five-minute answer.
  • When the scope is agreed, the customer signs with the built-in e-signature, and the scope they signed is the one on record.

Builders and fit-out firms can see more on quoting for construction companies. Ella, who estimates for a Cardiff refurbishment firm, says the comment feature alone has saved her a dozen site visits this year, because customers ask the question in the document instead of saving it for the first morning on site.

If you would like a scope of works template built around your trade, talk to us.